|
By
PETER GRUNER and SUNITA RAPPAI
|
|
Further delays to Whittington build
|
THE future of a new £30-million wing at Archways
Whittington Hospital is still in the balance after health
bosses revealed a new company could take over the project from
troubled construction firm Jarvis.
Jarvis, suffering with cash-flow problems, is negotiating with
City financiers to take on the project.
But a new company could mean further delays for the building,
which was already nine months behind schedule when work stopped
in December.
And hospital bosses have admitted there is still no start date
in sight increasing fears that the scheme to replace the
crumbling Victorian wards wont be completed until the end
of the year.
The hospitals NHS Trust chairman Narendra Makanji told the
New Journal: It depends on the settling of 13 other Jarvis
projects and there are three parties involved. There is
Jarvis, financiers Star Capital who want to take over from Jarvis
and banks, which are in the main HSBC.
He said if a new firm took over the project they were likely to
bring in new builders, adding to the delays.
He added: But I am cautiously optimistic the wing will be
completed towards end of this year. You have to have deadlines
with builders or things just go on and on. But even after a takeover,
there will be at least a month before physical work is started.
Jarvis won the contract to design, build and maintain the new
wing under a Private Finance Initiative (PFI) in October 2002
to replace wards built in the 1800s and Jarvis was
chosen ahead of two other companies under the PFI agreement.
The deal with Jarvis, which would see the company maintain the
wing, was due to run for 30 years.
|